Forum Replies Created
-
AuthorPosts
-
admin
KeymasterThe correct answer is D.
Choices A and B are good ideas, but they do not solve the problem presented in the question. The WBS (choice A) and the project charter (choice B) do not identify stakeholders. Choice C is a procurement function.
Revise Communication Management Concepts: Project Communication Management
admin
KeymasterThe correct answer is A.
Remember that for variances, negative is bad. In this situation, both the variances are negative. To answer the question, first look for which one of the four choices exhibits negative variances for both cost and schedule. Choice B exhibits negative variance for cost and positive variance for schedule. Choice C exhibits positive variance for cost and negative variance for schedule. Choice D exhibits positive variances for both. Only choice A exhibits both cost and schedule variances as negative.
Revise Cost Management Concepts: Project Cost Management
admin
KeymasterThe correct answer is A.
Did you realize this question describes secondary risks? Identifying secondary risks is good and expected while completing the Plan Risk Responses process. With that in mind, the best thing to do is choice A.
Revise Risk Management Concepts: Project Risk Management
admin
KeymasterThe correct answer is D.
Choice A refers to lessons learned, and choices B and C are always part of closure. When project closure occurs at the end of the project (as opposed to at the end of a phase), the project management plan would not need to be updated (choice D).
Revise Project Integration Management Concepts: Project Integration Management
admin
KeymasterThe correct answer is A.
Choice B is part of the closing process group. Choice C occurs during the initiating process group. Since choice D is a planning function, it must take place during the planning process group. Choice A is done in the executing process group, as part of the Manage Project Team process.
Revise Project Management Fundamentals Concepts: Project Management Fundamentals
admin
Keymasteradmin
KeymasterThe correct answer is D.
Choice A is incorrect, as the change would not impact the entire project management process, only procurement. Loyalty to the project (choice B) would be gained, not lost, in a decentralized environment. In a decentralized procurement situation, there is less focus on maintaining the skill or expertise of the contracting function, making choice D the best answer.
Revise Procurement Management Concepts: Project Procurement Management
admin
KeymasterThe correct answer is C.
Choices A and B would only make the problem worse. Choice D would help you see how much of a problem you have, but would not solve the problem. Only a quality audit (choice C) leads to solving the problem.
Revise Quality Management Concepts: Project Quality Management
admin
KeymasterThe correct answer is C.
You know that cutting all activities by 10 percent is not good project management, so choice B is obviously incorrect. Meeting with management to review scope (choice D) would be of no help since this has already occurred. The best alternative would be fast tracking, or doing activities in parallel. This provides focus on the critical path.
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is D.
The work breakdown structure is designed to show all the work that is required to produce the project output as well as the other project-specific activities. It should include enough detail to allow you to manage the project with the resulting work packages.
Revise Scope Management Concepts: Project Scope Management
admin
KeymasterThe correct answer is B.
The key words here are “first two weeks.” When you first organize a team, you need to provide the direction. After they become self-motivated, you could use one of the other leadership styles.
Revise Resource Management Concepts: Project Resource Management
admin
KeymasterThe correct answer is D.
Choices C and D both include nonverbal communication, which represents 55 percent of communication. Choice D adds paralingual communication (pitch and tone) and is thus the best choice.
Revise Communication Management Concepts: Project Communication Management
admin
KeymasterThe correct answer is A.
EV is the value of the work completed. In this case, one side is done ($11 x 125 = $1,375), 75 feet of the second side is done ($11 x 75 = $825) and the culvert is complete ($500) for a total of $2,700. Since the AC is $2,700, CV = $0. You are budget neutral.
Revise Cost Management Concepts: Project Cost Management
admin
KeymasterThe correct answer is C.
This is the Perform Qualitative Risk Analysis process. Only activity which is left out is the probability and impact matrix development.
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
admin
KeymasterThe correct answer is A.
Did this one trick you? Normally, one would report a copyright violation. Here there isn’t a copyright violation. The family member is offering, they have not already done it. This is why the correct answer is A.
Revise Project Integration Management Concepts: Project Integration Management
-
AuthorPosts