KeymasterCorrect answer is B.
Other than what is mentioned in choice B, all other information is included in the stakeholder engagement plan. What is mentioned under choice B is included in the stakeholder register, not stakeholder management plan.
Pass PMP in the First Attempt : PMP Strategy
Revise Stakeholder Management Concepts: Project Stakeholder Management
admin
KeymasterThe correct answer is A.
There are certain basic things that should go into all contracts; an arbitration (or dispute resolution) clause is one of them.
Pass PMP in the First Attempt : PMP Strategy
Revise Procurement Management Concepts: Project Procurement Management
admin
KeymasterThe correct answer is B.
The group is using organizational process assets to improve their project. Although the incident just occurred, it was on another project. They are in the Plan Quality process.
Pass PMP in the First Attempt : PMP Strategy
Revise Quality Management Concepts: Project Quality Management
admin
KeymasterThe correct answer is D.
Choice D treats all team members with respect and preserves an individual’s integrity while identifying gaps in the project scope statement. It also allows the project manager to interpret body language of those who misunderstood.
Pass PMP in the First Attempt : PMP Strategy
Revise Scope Management Concepts: Project Scope Management
admin
KeymasterThe correct answer is B.
Both parties are giving up something. This is a compromise.
Pass PMP in the First Attempt : PMP Strategy
Revise Resource Management Concepts: Project Resource Management
admin
KeymasterThe correct answer is C.
Total float and free float (choices A and B) are the time an activity can be delayed without impacting the entire project or the next activity. CPM (choice D) is a network analysis technique, not waiting time. Choice C is the correct answer.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is A.
Resource leveling (choice B) involves analysis of the number of resoures used. Choice C occurs before the team is selected. Choice D occurs after the team has been selected. The team is trying to respond to a risk by changing a resource. The answer is choice A.
Pass PMP in the First Attempt : PMP Strategy
Revise Risk Management Concepts: Project Risk Management
admin
KeymasterThe correct answer is C.
Many project managers spend all their time while the work is being done issuing and using status reports. Great project managers know these are necessary, but are not a replacement for properly managing a project. By interacting with the team, watching what is going on, and listening to the team members, you will find out sooner than later what the “real” status of the project is. Reports are normally a week or two behind the actual work, causing a delay in reacting to problems. Therefore, choice C is the biggest disadvantage.
Pass PMP in the First Attempt : PMP Strategy
Revise Communication Management Concepts: Project Communication Management
admin
KeymasterThe correct answer is B.
A cost baseline must include a contingency reserve for risks. It does not include a management reserve (choice C). Choices A and D should have been completed earlier.
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP Concepts: PMP Concepts
admin
KeymasterStakeholder analysis follows 3 steps as described under choices B, C, and D. activity described under choice A is performed during Plan Stakeholder Engagement process.
Pass PMP in the First Attempt : PMP Strategy
Revise Stakeholder Management Concepts: Project Stakeholder Management
admin
KeymasterThe correct answer is C.
As the project manager, you know what the project risks are. You need to make sure that provisions are included in the contract to address these risks.
Pass PMP in the First Attempt : PMP Strategy
Revise Procurement Management Concepts: Project Procurement Management
admin
KeymasterThe correct answer is C.
Although quality planning usually occurs during project planning, sometimes we need to go back to planning from other processes to make a decision.
Pass PMP in the First Attempt : PMP Strategy
Revise Quality Management Concepts: Project Quality Management
admin
KeymasterThe correct answer is C.
The wider the range between the optimistic and pessimistic estimates in a three-point estimate, the more uncertainty the estimator has.
Pass PMP in the First Attempt : PMP Strategy
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is C.
Choices A, B, and D are processes in the monitoring and controlling process group. This situation asks how to prevent the problem. This would have been done during the planning processes. The project deliverables are defined in the Define Scope process (choice C), which is a part of project planning. Good planning reduces the likelihood of a situation like the one described by including the right people and spending adequate time in clarifying the project scope.
Pass PMP in the First Attempt : PMP Strategy
Revise Scope Management Concepts: Project Scope Management
admin
KeymasterThe correct answer is C.
Choice D, the most common incorrect answer, ignores the issue. Here the project manager is not ignoring. The project manager is saying the issue is valid but he/she does not think it will be a real problem later.
Pass PMP in the First Attempt : PMP Strategy
Revise Resource Management Concepts: Project Resource Management
-
AuthorPosts