KeymasterThe correct answer is D.
Both critical paths have durations of 16 weeks. Since 16 weeks is the longest duration of paths, you have two critical paths.
Pass PMP in the First Attempt : PMP Strategy
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is D.
The process they have used so far is fine, except the input of other stakeholders is needed in order to identify more risks.
Pass PMP in the First Attempt : PMP Strategy
Revise Risk Management Concepts: Project Risk Management
admin
KeymasterThe correct answer is A.
Cost accounts are included in the project cost estimate, and the contingency reserve is added to that to come up with the cost baseline. Thereafter, the management reserve is added to come up with the cost budget.
Pass PMP in the First Attempt : PMP Strategy
Revise Cost Management Concepts: Project Cost Management
admin
KeymasterCorrect answer is A.
Project Management Plan, Issue log, and Work performance data are required.
Pass PMP in the First Attempt : PMP Strategy
Revise Stakeholder Management Concepts: Project Stakeholder Management
admin
KeymasterThe correct answer is C.
If it is not in the contract (which includes the specifications), a change order is needed to acquire it.
Pass PMP in the First Attempt : PMP Strategy
Revise Procurement Management Concepts: Project Procurement Management
admin
KeymasterThe correct answer is C.
The key words here are “identifying the quality standards” which is done in the Plan Quality Management process.
Pass PMP in the First Attempt : PMP Strategy
Revise Quality Management Concepts: Project Quality Management
admin
KeymasterThe correct answer is B.
You need to first understand the change before you can evaluate it. In this instance, verbal communication is not likely to provide enough information to evaluate. Once you understand the change, you can work with the team to determine the impact and options.
Pass PMP in the First Attempt : PMP Strategy
Revise Scope Management Concepts: Project Scope Management
admin
KeymasterThe correct answer is B.
This question tests if you understand that functional managers generally “own” or control the resources on projects. It would not be professionally responsible to try to keep a resource if he can be replaced without hurting the project (choice A). Choice C cannot be best because it is not the resource’s job to find a replacement. Choice D cannot be best, as waiting might impact the project. By talking to the functional manager, the project manager can find out if the team member will be selected for the other project and see if there really is a problem.
Pass PMP in the First Attempt : PMP Strategy
Revise Resource Management Concepts: Project Resource Management
admin
KeymasterCorrect answer is D.
Previous communication channels = n*(n-1)/2 = 5*(5-1)/2 = 10
New communication channels = n*(n-1)/2 = 7*(7-1)/2 = 21
Additional channels = 21 – 10 = 11
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
admin
KeymasterThe correct answer is D.
This question tests whether you know how to solve problems, especially if you are one of those project managers who has not realized that an unrealistic schedule is something you should deal with before beginning work. Since cutting product scope affects the customer, choice A has a great negative effect and is therefore not best. A project manager’s job is to determine options for meeting any end date or time, therefore choice B cannot be correct. Working overtime (choice C) is expensive and unnecessary when there are many other choices that could be selected first. Choice D could have the least negative effect on the project.
Pass PMP in the First Attempt : PMP Strategy
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is C.
The risk is the loss of data due to a power outage. Choice A is not related to “mitigating” the problem. It transfers the risk. A reserve fund (choice B) is acceptance and would help address the cost factors after the power failure, but would not reduce the probability or impact of it. Avoiding the hurricane by scheduling the installation at a different time (choice D) mitigates the power outage risk but could have a large negative impact on the project schedule and so is not the best choice. The better choice of the mitigation options (choices C and D) is to monitor the weather and know when to implement the contingency plan.
Pass PMP in the First Attempt : PMP Strategy
Revise Risk Management Concepts: Project Risk Management
admin
KeymasterThe correct answer is C.
Re-estimating activity attributes provides extra information whether the cost estimates are proper or not.
Pass PMP in the First Attempt : PMP Strategy
Revise Cost Management Concepts: Project Cost Management
admin
KeymasterCorrect answer is D.
Operational stakeholders are the ones who will perform their work by using outputs of operation/production from the product/service/or result delivered by the project. Suppliers provide resources or services to complete the project. Suppliers are not operational stakeholders.
Pass PMP in the First Attempt : PMP Strategy
Revise Stakeholder Management Concepts: Project Stakeholder Management
admin
KeymasterThe correct answer is D.
In a procurement situation, generally only the procurement manager has the authority to sign changes. Sometimes the project manager has certain expanded authority to sign in the event of an emergency. However, an increase in cost is generally not considered an emergency. Choice A is not appropriate, since in this case, a procurement manager must sign a change. Reporting (choice B) will take too long, and should not be necessary. An extension (choice C) will not help in this situation.
Pass PMP in the First Attempt : PMP Strategy
Revise Procurement Management Concepts: Project Procurement Management
admin
KeymasterThe correct answer is B.
Choices A and C are already stated, because the two items are listed as problems. They may be true, but they are not answers to the question. It would be best to determine if the problems are related (choice B) before planning what to do about them.
Pass PMP in the First Attempt : PMP Strategy
Revise Quality Management Concepts: Project Quality Management
-
AuthorPosts