Forum Replies Created
-
AuthorPosts
-
admin
KeymasterThe correct answer is A.
You are training the team on skills required for the project. The cost is directly related to the project and thus a direct cost.
Pass PMP in the First Attempt : PMP Strategy
Revise Cost Management Concepts: Project Cost Management
admin
KeymasterCorrect answer is D.
OPAs updates are same in both processes, except lessons learned.
Pass PMP in the First Attempt : PMP Strategy
Revise Stakeholder Management Concepts: Project Stakeholder Management
admin
KeymasterThe correct answer is A.
A project manager must understand the legal implications of her actions. A contract is a legally binding document. Choice B involves just making notes. It does nothing to resolve the issue, so it cannot be best. There is no reason for the buyer to terminate (choice C), just because the seller does not want to continue. A signed contract is legally binding. If you selected choice D first, the seller could be taking such action as stopping work, removing resources, or otherwise negatively impacting the project while you are holding the meeting. It is best to first remind the seller that he is legally bound to continue. You could follow up that action with choice D.
Pass PMP in the First Attempt : PMP Strategy
Revise Procurement Management Concepts: Project Procurement Management
admin
KeymasterThe correct answer is D.
A project manager must always evaluate the situation before recommending a corrective action or a change.
Pass PMP in the First Attempt : PMP Strategy
Revise Quality Management Concepts: Project Quality Management
admin
KeymasterThe correct answer is A.
A change in cost may not affect the time a project takes to complete (choice B). There is nothing in the question to suggest that the methods to find and make changes (choice C) are faulty. Choice D is a made-up term. When such a problem occurs, it is important to see if anything else has been forgotten (choice A).
Pass PMP in the First Attempt : PMP Strategy
Revise Scope Management Concepts: Project Scope Management
admin
KeymasterThe correct answer is D.
A risk analysis (choice A) may help, but not as much as a resource-limited schedule (choice D). A responsibility assignment matrix (choice B) shows who is responsible for what, as does a responsibility chart (choice C). They will not help you manage the project with limited resources. Only D will help meet the defined need.
Pass PMP in the First Attempt : PMP Strategy
Revise Resource Management Concepts: Project Resource Management
admin
KeymasterThe correct answer is A.
The key words here are “performance over time.” A forecasting report (choice B) looks only to the future. A status report (choice C) is generally static (relating to a moment in time). A variance report (choice D) looks at specific project items or activities compared to the plan. The only choice that addresses performance “over time” is a trend report (choice A).
Pass PMP in the First Attempt : PMP Strategy
Revise Communication Management Concepts: Project Communication Management
admin
KeymasterThe correct answer is C.
The key to this question is the phrase “constant number used each month.” Only leveling, choice C, has such an effect on the schedule.
Pass PMP in the First Attempt : PMP Strategy
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is B.
To mitigate risk (choice A) we either reduce the probability of the event happening or reduce its impact. Many people think of using insurance as a way of decreasing impact. However, mitigating risk is taking action before a risk event occurs. Acceptance of risk (choice C) does not involve such action as purchasing insurance. Avoidance of risk (choice D) means that we change the way we will execute the project so the risk is no longer a factor. Transference is passing the risk off to another party.
Pass PMP in the First Attempt : PMP Strategy
Revise Risk Management Concepts: Project Risk Management
admin
KeymasterThe correct answer is B.
Setup costs do not change as production on the project changes. Therefore, they are fixed costs.
Pass PMP in the First Attempt : PMP Strategy
Revise Cost Management Concepts: Project Cost Management
admin
KeymasterCorrect answer is a.
Stakeholder requirements are collected during Collect requirements process and mentioned in the Requirements Documentation.
Pass PMP in the First Attempt : PMP Strategy
Revise Stakeholder Management Concepts: Project Stakeholder Management
admin
KeymasterThe correct answer is C.
Such a tour is part of the procurement process called Conduct Procurements. Conduct Procurements occurs during project executing.
Pass PMP in the First Attempt : PMP Strategy
Revise Procurement Management Concepts: Project Procurement Management
admin
KeymasterThe correct answer is B.
The key word here is “overall.” Control Quality (choice D) is incorrect because we are not addressing the specific work performance. Manage Quality process is used to make sure standards and processes were followed.
Pass PMP in the First Attempt : PMP Strategy
Revise Quality Management Concepts: Project Quality Management
admin
KeymasterThe correct answer is C.
If you picked project charter (choice B) remember that the project charter is a high-level document. Because the WBS dictionary (choice C) is much more detailed, it would provide more help in controlling gold plating.
Pass PMP in the First Attempt : PMP Strategy
Revise Scope Management Concepts: Project Scope Management
admin
KeymasterThe correct answer is D.
This is an example of conflict and a choice of conflict resolution techniques. The project manager is withdrawing.
Pass PMP in the First Attempt : PMP Strategy
Revise Resource Management Concepts: Project Resource Management
-
AuthorPosts
