KeymasterThe correct answer is B.
It is imperative that requirements be as clear as possible before the project management plan is finalized. Only problem solving, described in choice B, helps achieve this. Choice A is smoothing, choice C is avoidance and choice D is forcing.
Pass PMP in the First Attempt : PMP Strategy
Revise Scope Management Concepts: Project Scope Management
admin
KeymasterThe correct answer is C.
Rewards, used correctly, bring the team’s objectives in line with each other and with the project.
Pass PMP in the First Attempt : PMP Strategy
Revise Resource Management Concepts: Project Resource Management
admin
KeymasterThe correct answer is C.
Choice A cannot be correct because the question states that all stakeholders received the information. Choices B and D do not address the root cause of the problem. The problem presented here shows that there is something missing in the communications management plan. The best answer is to review the communications management plan in order to prevent future problems and find any instances of similar problems.
Pass PMP in the First Attempt : PMP Strategy
Revise Communication Management Concepts: Project Communication Management
admin
KeymasterThe correct answer is A.
Organizational process assets include historical information. Such information about previous projects should be considered while defining project activities, especially information about errors and omissions on previous projects. Choice B is a subset of choice A. The staff assignments from a previous project are part of organizational process assets, and therefore part of the historical information to consider when planning a similar project.
Pass PMP in the First Attempt : PMP Strategy
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is A.
The first choice would be to review the risk. Reserves may or may not be used, as in choice D.
Pass PMP in the First Attempt : PMP Strategy
Revise Risk Management Concepts: Project Risk Management
admin
KeymasterThe correct answer is C.
To find the answer, look for things that would cause a poor estimate. A project management plan (choices A and D) comes after the creation of estimates. Risk assessments (choices B and D) normally occur after estimating.
Pass PMP in the First Attempt : PMP Strategy
Revise Cost Management Concepts: Project Cost Management
admin
KeymasterCorrect answer is C.
Stakeholder engagement Plan contains:
1. Stakeholder communication requirements
2. Information to be distributed
3. Reason for distribution and expected impact to stakeholder engagement
4. Time frame and frequency for distributionPass PMP in the First Attempt : PMP Strategy
Revise Stakeholder Management Concepts: Project Stakeholder Management
admin
KeymasterThe correct answer is A.
This is not a core competency of the company. There is time and data for a detailed procurement statement of work. In this case, it is better to shift risk to another company.
Pass PMP in the First Attempt : PMP Strategy
Revise Procurement Management Concepts: Project Procurement Management
admin
KeymasterThe correct answer is A.
Only a quality management plan is not an output of Control Quality.
Pass PMP in the First Attempt : PMP Strategy
Revise Quality Management Concepts: Project Quality Management
admin
KeymasterThe correct answer is B.
The rules of the Delphi technique are: keep the experts’ identities anonymous, do not bring the experts together in the same room, and build consensus.
Pass PMP in the First Attempt : PMP Strategy
Revise Scope Management Concepts: Project Scope Management
admin
KeymasterThe correct answer is C.
The staffing management plan describes when resources will be brought onto and taken off the project.
Pass PMP in the First Attempt : PMP Strategy
Revise Resource Management Concepts: Project Resource Management
admin
KeymasterThe correct answer is C.
Since the dependency is required, it could not be discretionary (choice A) and therefore must be mandatory. No mention is made that the dependency comes from a source outside the project, so external (choice B) is not correct. Scope dependency (choice D) is not a defined term. The key word in this question is “requires.” The question defines a mandatory dependency.
Pass PMP in the First Attempt : PMP Strategy
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is A.
This is the definition of the risk response strategy of avoidance.
Pass PMP in the First Attempt : PMP Strategy
Revise Risk Management Concepts: Project Risk Management
admin
KeymasterThe correct answer is B.
Written communication allows your words to be documented, and they will go to everyone in the same form. When there are complex problems, you want everyone to receive the same thing.
Pass PMP in the First Attempt : PMP Strategy
Revise Communication Management Concepts: Project Communication Management
admin
KeymasterThe correct answer is A.
In this situation, the company might have to pay large fines. It is best to ask for legal advice.
Pass PMP in the First Attempt : PMP Strategy
Revise Cost Management Concepts: Project Cost Management
-