admin
KeymasterThe correct answer is D.
The project manager’s responsibility is to provide truthful project information. He or she should thereafter discuss the impacts of their actions with the team members. If that does not work, the next step is to report it to their functional managers.
Pass PMP in the First Attempt : PMP Strategy
Revise Communication Management Concepts: Project Communication Management
admin
KeymasterCorrect answer is c.
There is no duration for the milestone.
Pass PMP in the First Attempt : PMP Strategy
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is C.
The activities of the Perform Qualitative Risk Analysis process are probability and impact definition, assumptions testing (data quality assessment), and probability and impact matrix development.
Pass PMP in the First Attempt : PMP Strategy
Revise Risk Management Concepts: Project Risk Management
admin
KeymasterThe correct answer is C.
Choice A could be done, but historical information is not enough. Choices B and D are not correct because you are still in project initiating. You have not yet identified activities, nor do you have a schedule model. It is best to provide estimates based on an understanding of this project, so the best answer is choice C.
Pass PMP in the First Attempt : PMP Strategy
Revise Cost Management Concepts: Project Cost Management
admin
KeymasterCorrect answer is A.
Communications management plan does not document identified interrelationships and potential overlap between stakeholders. This item is mentioned in the stakeholder engagement plan.
Pass PMP in the First Attempt : PMP Strategy
Revise Stakeholder Management Concepts: Project Stakeholder Management
admin
KeymasterThanks for pointing it out. Will update the question. Resource Requirement & Change Requests both are the correct answers.
admin
KeymasterSure. Can you please share the question?
admin
KeymasterThe correct answer is A.
Notice that choice B is really saying “halt all payments.” Halting all payments would be a breach of contract on the buyer’s part. Choice C is too severe and cannot be done unilaterally. Choice D does not solve the problem presented. The best answer is A.
Pass PMP in the First Attempt : PMP Strategy
Revise Procurement Management Concepts: Project Procurement Management
admin
KeymasterThe correct answer is B.
The group is using organizational process assets to improve their project. Although the incident just occurred, it was on another project. They are in the Plan Quality process.
Pass PMP in the First Attempt : PMP Strategy
Revise Quality Management Concepts: Project Quality Management
admin
KeymasterThe correct answer is D.
A project manager cannot be responsible for the customer’s inspection process (choice A), only his own. Network diagram changes (choice B) will not affect the root cause of this problem. An apology (choice C) might be in order later, after the root cause is found. The best choice of those provided is to review the Validate Scope process (choice D) as that process deals with acceptance by stakeholders.
Pass PMP in the First Attempt : PMP Strategy
Revise Scope Management Concepts: Project Scope Management
admin
KeymasterThe correct answer is A.
Formal power is based on your position.
Pass PMP in the First Attempt : PMP Strategy
Revise Resource Management Concepts: Project Resource Management
admin
KeymasterThe correct answer is D.
The professional and social responsibility of the project manager requires that the truth be told. Choice A is lying and unethical. Choice B is not the correct choice because you do not KNOW the project will be late. There is time to fix the problems. Choice C is not correct because there are no cost problems illustrated in the question. As in any report, you need to state the issues and options.
Pass PMP in the First Attempt : PMP Strategy
Revise Communication Management Concepts: Project Communication Management
admin
KeymasterThanks for raising the query.
Please read page 123 carefully. It is written “The activities necessary for the administrative closure of the project or phase include but are not limited to:”.Moreover, it is not in the specific order. It is simply the list.
admin
Keymasteradmin
KeymasterAnswer – Create an activity list
After WBS, WBS Dictionary creation, next step is to Define Activities.
-