KeymasterThe correct answer is C.
Penalty power refers to removing some benefit.
Pass PMP in the First Attempt : PMP Strategy
Revise Resource Management Concepts: Project Resource Management
admin
KeymasterThe correct answer is D.
Understanding the receiver’s perspective allows you to direct the communication to meet his needs.
Pass PMP in the First Attempt : PMP Strategy
Revise Communication Management Concepts: Project Communication Management
admin
KeymasterThe correct answer is B.
You need to draw a network diagram for this question. This diagram has two paths: Start, 1, 2, 3, End and Start, 1, 4, End. The original length of the first path is 10 and the second is 9, making the first path critical and the length of the critical path 10. If Activity 4 now takes 10 weeks instead of 8, the critical path would change to Start, 1, 4, End and be 11 weeks long.
Pass PMP in the First Attempt : PMP Strategy
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is A.
The first choice would be to review the risk. Reserves may or may not be used, as in choice D.
Pass PMP in the First Attempt : PMP Strategy
Revise Risk Management Concepts: Project Risk Management
admin
KeymasterDue to quiz software issue, diagrams are not being shown at the moment. Currently working with the software vendor for the issue resolution. Sorry for inconvenience.
admin
KeymasterThe correct answer is C.
EV is determined from a total budget of $10,000 and a five week duration. Each week would be $2,000. Therefore, for two weeks of completed work, we have an EV of $4,000. CV = EV – AC, CV = $4000 – $2000 = $2,000. Positive means you are under budget.
Pass PMP in the First Attempt : PMP Strategy
Revise Cost Management Concepts: Project Cost Management
admin
KeymasterThe correct answer is D.
Option A is done during Manage Stakeholder Engagement process. Option B doesn’t make any sense. Option C doesn’t occur in Monitor Stakeholder Engagement process.
Pass PMP in the First Attempt : PMP Strategy
Revise Stakeholder Management Concepts: Project Stakeholder Management
admin
KeymasterThe correct answer is A.
Centralized contracting usually means it is more difficult to get access to the procurement manager, and the procurement manager has less loyalty. Therefore, choices B and D are disadvantages. The fact that procurement managers has no home when they’re not working on a project (choice C) is also a disadvantage.
Pass PMP in the First Attempt : PMP Strategy
Revise Procurement Management Concepts: Project Procurement Management
admin
KeymasterThe correct answer is A.
Quality is defined as conformance to requirements and specifications. The best answer here is when the requirements have been met (choice A). We do not achieve quality if we exceed expectations (choice B), get a verbal OK (choice C), or stop adding features requested by the customer (choice D).
Pass PMP in the First Attempt : PMP Strategy
Revise Quality Management Concepts: Project Quality Management
admin
KeymasterSince the questions are being randomly picked at runtime from the question bank, can you please post the question here ?
admin
KeymasterThe correct answer is C.
Notice the use of the terms “product” and “project scope” and how they mean different things? Choice C is the best option, since a change to any part of the product or project should be evaluated for impacts to other parts.
Pass PMP in the First Attempt : PMP Strategy
Revise Scope Management Concepts: Project Scope Management
admin
KeymasterThe correct answer is A.
Generally, the best forms of power are reward or expert. The project manager has not had time to become a recognized expert in the company (choice D) and reward is not included as a choice here. This leaves formal power (choice A) as the only logical answer.
Pass PMP in the First Attempt : PMP Strategy
Revise Resource Management Concepts: Project Resource Management
admin
KeymasterThe correct answer is D.
The best choice is D. If informal verbal communication does not solve the problem, choice A is the next best choice. This does not mean that you do not keep records of the problem, but this question is asking about communication between two parties.
Pass PMP in the First Attempt : PMP Strategy
Revise Communication Management Concepts: Project Communication Management
admin
KeymasterThe correct answer is C.
You do not necessarily need to change the schedule, unless, of course, the delay is more than the activity’s float.
Pass PMP in the First Attempt : PMP Strategy
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is A.
This question relates real-world situations to risk types. Did you realize that the entire first paragraph is extraneous? Based on the question, you cannot delete the work to avoid it, nor can you insure or outsource to transfer the risk. This leaves acceptance as the only correct choice.
Pass PMP in the First Attempt : PMP Strategy
Revise Risk Management Concepts: Project Risk Management
-