Forum Replies Created
-
AuthorPosts
-
admin
KeymasterThe correct answer is C.
The key to this question is the phrase “constant number used each month.” Only leveling, choice C, has such an effect on the schedule.
Pass PMP in the First Attempt : PMP Strategy
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is B.
To mitigate risk (choice A) we either reduce the probability of the event happening or reduce its impact. Many people think of using insurance as a way of decreasing impact. However, mitigating risk is taking action before a risk event occurs. Acceptance of risk (choice C) does not involve such action as purchasing insurance. Avoidance of risk (choice D) means that we change the way we will execute the project so the risk is no longer a factor. Transference is passing the risk off to another party.
Pass PMP in the First Attempt : PMP Strategy
Revise Risk Management Concepts: Project Risk Management
admin
KeymasterThe correct answer is B.
Setup costs do not change as production on the project changes. Therefore, they are fixed costs.
Pass PMP in the First Attempt : PMP Strategy
Revise Cost Management Concepts: Project Cost Management
admin
KeymasterCorrect answer is a.
Stakeholder requirements are collected during Collect requirements process and mentioned in the Requirements Documentation.
Pass PMP in the First Attempt : PMP Strategy
Revise Stakeholder Management Concepts: Project Stakeholder Management
admin
KeymasterThe correct answer is C.
Such a tour is part of the procurement process called Conduct Procurements. Conduct Procurements occurs during project executing.
Pass PMP in the First Attempt : PMP Strategy
Revise Procurement Management Concepts: Project Procurement Management
admin
KeymasterThe correct answer is B.
The key word here is “overall.” Control Quality (choice D) is incorrect because we are not addressing the specific work performance. Manage Quality process is used to make sure standards and processes were followed.
Pass PMP in the First Attempt : PMP Strategy
Revise Quality Management Concepts: Project Quality Management
admin
KeymasterThe correct answer is C.
If you picked project charter (choice B) remember that the project charter is a high-level document. Because the WBS dictionary (choice C) is much more detailed, it would provide more help in controlling gold plating.
Pass PMP in the First Attempt : PMP Strategy
Revise Scope Management Concepts: Project Scope Management
admin
KeymasterThe correct answer is D.
This is an example of conflict and a choice of conflict resolution techniques. The project manager is withdrawing.
Pass PMP in the First Attempt : PMP Strategy
Revise Resource Management Concepts: Project Resource Management
admin
KeymasterThe correct answer is D.
The project manager’s responsibility is to provide truthful project information. He or she should thereafter discuss the impacts of their actions with the team members. If that does not work, the next step is to report it to their functional managers.
Pass PMP in the First Attempt : PMP Strategy
Revise Communication Management Concepts: Project Communication Management
admin
KeymasterCorrect answer is c.
There is no duration for the milestone.
Pass PMP in the First Attempt : PMP Strategy
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is C.
The activities of the Perform Qualitative Risk Analysis process are probability and impact definition, assumptions testing (data quality assessment), and probability and impact matrix development.
Pass PMP in the First Attempt : PMP Strategy
Revise Risk Management Concepts: Project Risk Management
admin
KeymasterThe correct answer is C.
Choice A could be done, but historical information is not enough. Choices B and D are not correct because you are still in project initiating. You have not yet identified activities, nor do you have a schedule model. It is best to provide estimates based on an understanding of this project, so the best answer is choice C.
Pass PMP in the First Attempt : PMP Strategy
Revise Cost Management Concepts: Project Cost Management
admin
KeymasterCorrect answer is A.
Communications management plan does not document identified interrelationships and potential overlap between stakeholders. This item is mentioned in the stakeholder engagement plan.
Pass PMP in the First Attempt : PMP Strategy
Revise Stakeholder Management Concepts: Project Stakeholder Management
admin
KeymasterThanks for pointing it out. Will update the question. Resource Requirement & Change Requests both are the correct answers.
admin
KeymasterSure. Can you please share the question?
-
AuthorPosts