Forum Replies Created
-
AuthorPosts
-
admin
KeymasterThe correct answer is D.
Choice D is an example of compromising.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is C.
Resource leveling refers to keeping the number of resources the same and letting time and cost be flexible.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is C.
Some people may think this question has more than one right answer. It does not. There are many things the project manager can do, but what should be done? The company policies are managed by the project management office, and the project manager should make sure the stakeholders have clear information by sending them directly to the authority on company policies for project management.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is D.
A project manager must manage a project. If all activities are delegated, chaos ensues and team members will spend more time jockeying for position than completing activities.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is C.
Choice D, the most common incorrect answer, ignores the issue. Here the project manager is not ignoring. The project manager is saying the issue is valid but he/she does not think it will be a real problem later.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is C.
This is a question with more than one right answer. The question is really asking which is MOST important. The easiest way to deal with these questions is to look for the choice that will have the biggest impact on the project. Choice A is important, but look again at choice C. It is a method of recording the change, like choice A, but it is more specific and detailed. Be careful about choices like D. Changes are not bad and should not generally be prevented.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is A.
The question is really asking, “What is done after Estimate Activity Durations?” All of the activities listed except choice A are done before Estimate Activity Durations.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is D.
Fringe benefits are included in overhead and are part of indirect costs.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is C.
This is a large effort. No procurement statement of work can be developed, and expertise cannot be found internally. CPIF would be an incentive to the vendor to perform on or ahead of schedule.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is D.
Because the CEO is the sponsor, choices A and B would not be good first choices. Choice B might be done after choice D. Choice C is often done before a project is selected.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is A.
Having more resources does not generally make it HARDER to use reward power (choice B). Choice C is an incorrect statement. Choice D does not make sense, so it cannot be the correct answer. This leaves only choice A.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is C.
The only choice listed that makes sense and is an input to Manage Quality is choice C.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is A.
Cost increases (choice B) and contract disputes (choice C) will not necessarily interfere with schedule. Notice the words “post-implementation” in choice D. It will not definitely interfere with the project schedule. Choice A is the only one that deals with a time delay.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is A.
The project manager’s decision is to find a middle ground. This is compromise.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is A.
Major project constraints include scope, time, cost, quality, risk, resources, and customer satisfaction. This question talks about a change in scope. It would be most important to look for impacts to other project constraints. After that is completed, the impact to subsequent work packages would be evaluated.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
-
AuthorPosts
