CEO of a company has assigned a project manager to a project that the CEO wanted to do for a long time. What should the project manager do FIRST?
a) Assist the CEO in putting together a benefit cost analysis to show the need for the project.
b) Work with the CEO to get buy in from other stakeholders
c) Produce a ranking of all feasible projects , including the assigned project, in a weighted
scoring of decision variables.
d) Guide the creation of a project charter