    CEO of a company has assigned a project manager to a project that the CEO wanted to do for a long time. What should the project manager do FIRST?

    a) Assist the CEO in putting together a benefit cost analysis to show the need for the project.
    b) Work with the CEO to get buy in from other stakeholders
    c) Produce a ranking of all feasible projects , including the assigned project, in a weighted
    scoring of decision variables.
    d) Guide the creation of a project charter

    #4306
    admin
    Keymaster

    The correct answer is D.

    Because the CEO is the sponsor, choices A and B would not be good first choices. Choice B might be done after choice D. Choice C is often done before a project is selected.

    Pass PMP in the First Attempt : PMP Strategy

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.