admin
KeymasterCorrect answer is C.
Since the burn-up chart is steadily increasing, therefore, the slope i.e. velocity is same. As velocity represents the number of story points completed per iteration, therefore, number of story points completed per iteration is constant.
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
Team should complete (development and testing) 4 stories worth 18 story points. In the iteration retrospective, team can discuss the reasons of not meeting the target and then can plan accordingly for future iterations.
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is C.
Team should complete (development and testing) 4 stories worth 18 story points. In the iteration retrospective, team can discuss the reasons of not meeting the target and then can plan accordingly for future iterations.
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
This is an example of Avoiding risk.
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
Organizational process assets include historical information. This information would prove highly beneficial if Sara would review the details of the previous project. She may check the risks, mistakes, skills sets required, etc. of the previous project.
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
After completion of WBS and WBS dictionary, activity list is generated.
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
Power based upon the position is formal power.
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
Buyer and Seller are supposed to be bound by the contract. If the change is required then contract should be updated and agreed upon by both the parties and only then that change is supposed to be made in the deliverable.
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
There is no specified time within which the target is to be achieved.
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is D.
There is no specified time within which the target is to be achieved.
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
In this situation, schedule developed based upon resource limitation is most helpful to the Project Manager. This will help him to plan activities and show the true picture of schedule to all stakeholders.
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is B.
In XP, there is collective code ownership so that the knowledge is spread across the team. But in FDD, code areas have single owner to have consistency.
Agile Useful Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is B.
In XP, there is collective code ownership so that the knowledge is spread across the team. But in FDD, code areas have single owner to have consistency.
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
Ideal days estimation is the estimation without any interrupts in between. It remains same irrespective of who is working upon the user story.
Agile Useful Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is C.
Ideal days estimation is the estimation without any interrupts in between. It remains same irrespective of who is working upon the user story.
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge -
AuthorPosts