Vinay, Project Manager, just reviewed and completed the WBS and the WBS dictionary with the help of his team. Vicky, Project Sponsor, asked Vinay to publish risk register and responsibility assignment matrix so that everyone on the team would know about their roles. What Vinay should do next?
a. Create activity list
b. Identify roles and responsibilities of team members
c. Identify risks
d. Create project management plan