Forum Replies Created
-
AuthorPosts
-
admin
KeymasterThe correct answer is D.
The question states that internal measures have already been created. Therefore, external ones are needed. Only choice D helps benchmark externally.
Revise Quality Management Concepts: Project Quality Management
admin
KeymasterThe correct answer is B.
Since an activity with float will not affect the project duration as long as any delay is not greater than the float, choice A could not be best. Choice C cannot be best as this situation is not related to scope, just time. An activity with free float means it has time where it can be delayed without impacting the next activity. Therefore, choice D cannot be best. Any delay in when an activity is to be completed will most likely impact resources.
Revise Schedule Management Concepts: Project Schedule Management
admin
KeymasterThe correct answer is A.
If the scope change had been properly recorded, the change impact could have been addressed immediately.
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is A.
The project manager’s decision is to find a middle ground. This is compromise.
Pass PMP in the First Attempt : PMP Strategy
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is D.
You need to consider the needs of all your stakeholders.
Revise Communication Management Concepts: Project Communication Management
admin
KeymasterThe correct answer is B.
A full-time team member who completes her work sooner than planned could be forced to wait for the start of her next activity. Since she is full time, she would have to be paid for time not working.
Revise Cost Management Concepts: Project Cost Management
admin
KeymasterThe correct answer is D.
The process they have used so far is fine, except the input of other stakeholders is needed in order to identify more risks.
Revise Risk Management Concepts:
Project Risk Managementadmin
KeymasterThe correct answer is B.
Notice how the choices are similar to each other? Simply look at the first part of each choice “Control Scope focuses on ?” and see which of the two versions of the first part of the statement is correct. This eliminates choices A and D. Then read the second part of each choice. Choice C is partially correct and partially incorrect. Only choice B is completely correct.
Revise Project Integration Management Concepts: Project Integration Management
admin
KeymasterThe correct answer is C.
There are many things the project manager can do, but what should be done? The company policies are managed by the project management office, and the project manager should make sure the stakeholders have clear information by sending them directly to the authority on company policies for project management.
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP Concepts: PMP Concepts
admin
KeymasterCorrect answer is B.
Stakeholders have varying levels of responsibility and authority when participating on the project. This level can change over the course of the project’s life cycle.
Revise Stakeholder Management Concepts: Project Stakeholder Management
admin
KeymasterThe correct answer is D.
The best answer is D. Many people will select choice A, because, although they have learned from a textbook what a bidder conference is, they have never been there, and do not realize that the BEST thing is to make sure the sellers ask all their questions. Project managers should know that a seller’s competition (other sellers) will be in attendance, and sellers may not want to ask a question that gives away their edge to their competitors. If sellers? questions are not asked, it creates a risk of receiving less complete proposals from those sellers. That would make the procurement riskier. Without receiving and responding to the sellers’ questions, the buyer may make incorrect assumptions, and will be making decisions without all the facts.
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is C.
Choice A does not follow the rule to protect the best interests of the customer. Choice B does not solve the problem. Choice D will cause a default of contract. Although the deliverable meets the contractual requirements, it is best to bring the problem to the customer’s attention (choice C) so an option that does no harm can be found.
Revise Quality Management Concepts: Project Quality Management
admin
KeymasterThe correct answer is C.
Path 1 – Start 1, 2, 3, End
Path 2 – Start, 1, 2, 5, End
Path 3 – Start 1, 4, 5, EndPath 1 would take 4 + 8 + 5 days or 17 days to complete.
Path 2 would take 4 + 8 + 3 days or 15 days to complete.
Path 3 would take 4 + 8 + 3 days or 15 days to complete.
Therefore, Path 1 is critical pathPass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is B.
The project manager should validate with the customer that the change will add value, and then follow the change process.
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP Concepts: PMP Concepts
admin
KeymasterThe correct answer is A.
First action would be to find out whether working with family members is a common practice in that country (choice A), as there is nothing inherently illegal in this activity. Then, you would review qualifications (choice B). Choices C and D may not be necessary after choices A and B are done.
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP Concepts: PMP Concepts
-
AuthorPosts