KeymasterCorrect answer is C.
Earlier process efficiency = Value added time / Total Time = 18 / (18 + 36) = 33 %
Now process efficiency = Value added time / Total Time = 18 / (18 + 20) = 47 %
Imrpovement in Process Efficiency = 47% – 33% = 14%
Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
Helped, Hindered, Hypothesis is being used in the closing stage of retrospective in which we list down what helped during the retrospective, what were the hindrances and what hypothesis we would adopt in future retrospectives to make it more effective.
Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is D.
Helped, Hindered, Hypothesis is being used in the closing stage of retrospective in which we list down what helped during the retrospective, what were the hindrances and what hypothesis we would adopt in future retrospectives to make it more effective.
Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
According to Speed B. Leas, this situation is Level 4 conflict. In this level, conflict becomes more ideological and polarized and people feel that the other group is always wrong.
Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is C.
According to Speed B. Leas, this situation is Level 4 conflict. In this level, conflict becomes more ideological and polarized and people feel that the other group is always wrong.
Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
In Scrum, only fully completed user stories contributes towards velocity. Since User Stories 1, 2, and 3 are completed, therefore, they will contribute towards velocity.
Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is D.
In Scrum, only fully completed user stories contributes towards velocity. Since User Stories 1, 2, and 3 are completed, therefore, they will contribute towards velocity.
Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
In Scrum, it is the responsibility of the Product Owner to maintain and refine backlog. If any request comes, Product Owner should add it into the backlog and then priortize it so that it can be taken for development.Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is A.
In Scrum, it is the responsibility of the Product Owner to maintain and refine backlog. If any request comes, Product Owner should add it into the backlog and then priortize it so that it can be taken for development.Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
Confrontation is Problem solving method and is the best method to resolve the conflict.Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is B.
All improvement goals which the development team planned to take up in upcoming sprints are placed in the sprint backlog.Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is B.
All improvement goals which the development team planned to take up in upcoming sprints are placed in the sprint backlog.Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is B.
In the iteration planning, team discuss user stories and breaks them into tasks at the last responsible moment. Tasks are the smallest chunks of work required to build the story.Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
Quiz:
20 Questions Challenge 50 Questions ChallengeStudy Groups: Facebook Whatsapp Telegram
-
This reply was modified 2 years ago by
admin.
admin
KeymasterCorrect answer is B.
In the iteration planning, team discuss user stories and breaks them into tasks at the last responsible moment. Tasks are the smallest chunks of work required to build the story.Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
In ESVP, Prisoner is the one who thinks he is forcefully attending the meeting.Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
-
This reply was modified 2 years ago by
-
AuthorPosts