KeymasterCorrect answer is D.
Since the team is deciding what to do in the upcoming sprint, therefore, they are in the “Decide what to do” phase. Plus/Delta is being used in the Close Retrospective phase. All others are used in the “Decide what to do” phase.
Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is D.
Since the team is deciding what to do in the upcoming sprint, therefore, they are in the “Decide what to do” phase. Plus/Delta is being used in the Close Retrospective phase. All others are used in the “Decide what to do” phase.
Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
“Money for Nothing and Change for Free” has got benefits like changes will be free if total work remains same, buyer can cancel contract at any point of time by paying some percentage of the amount of the remaining work to offset supplier’s risk, product stays efficient as when remaining features are not valuable enough to develop then work can be stopped over it. In the Graduated Fixed-Price contract, is the supplier delivers on time then they get paid for the hours at the standard rate. But if they delivers early then they get paid for lesser hours but at the higher rate.
Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is D.
“Money for Nothing and Change for Free” has got benefits like changes will be free if total work remains same, buyer can cancel contract at any point of time by paying some percentage of the amount of the remaining work to offset supplier’s risk, product stays efficient as when remaining features are not valuable enough to develop then work can be stopped over it. In the Graduated Fixed-Price contract, is the supplier delivers on time then they get paid for the hours at the standard rate. But if they delivers early then they get paid for lesser hours but at the higher rate.
Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is B.
Command and control approach excludes team members from suggestions and planning processes. Putting suggestion to invite ideas of team members involve their participation which is more like servant leadership approach.
Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is B.
Command and control approach excludes team members from suggestions and planning processes. Putting suggestion to invite ideas of team members involve their participation which is more like servant leadership approach.
Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
Any type of goal should be SMART (Specific, Measurable, Attainable, Relevant, Timely). In this case, improvement goal is time bound (need to implement in next sprint), attainable (few team members already did it in other projects), and specific (reduce the time taken for release process). This is not measurable because it is not mentioned by how much time release process should be reduced.
Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is D.
Any type of goal should be SMART (Specific, Measurable, Attainable, Relevant, Timely). In this case, improvement goal is time bound (need to implement in next sprint), attainable (few team members already did it in other projects), and specific (reduce the time taken for release process). This is not measurable because it is not mentioned by how much time release process should be reduced.
Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
Agile works best when there is some uncertainty in both requirements and technology. If both are highly uncertain then Agile would not work in that case.
Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is C.
Agile works best when there is some uncertainty in both requirements and technology. If both are highly uncertain then Agile would not work in that case.
Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is B.
Best way to mitigate the risk is to provide training on conflict resolution techniques. This will equip team to resolve their conflicts and work together. Outsourcing, Insuring amd Removing are more like transferring and avoiding risks.
Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
As per Scrum, any change request (new requirement, defects) should go to the Product Backlog and then it should be prioritized by the Product Owner. If it critical enough then it can be prioritized accordingly so that it can be developed in the upcoming sprint.
Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is A.
As per Scrum, any change request (new requirement, defects) should go to the Product Backlog and then it should be prioritized by the Product Owner. If it critical enough then it can be prioritized accordingly so that it can be developed in the upcoming sprint.
Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
In Lean and Agile, documentation is just enough, just in time and whenever it is necessary. In the present case, for legal approval, document has to be in French language, otherwise our product cannot be approved. Therefore, it is necessary and not the form of waste.
Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is D.
In Lean and Agile, documentation is just enough, just in time and whenever it is necessary. In the present case, for legal approval, document has to be in French language, otherwise our product cannot be approved. Therefore, it is necessary and not the form of waste.
Video Tutorials : PM Video Tutorials
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge -
AuthorPosts