KeymasterCorrect answer is C.
Agile team collectively owns all the project features. As it is the severe issue, therefore, before making change, it would be better to analyze all available information and add it in the product backlog list at the appropriate place so that the team can pick up in the iteration backlog accordingly.
Tips/Tricks/Cheat sheet to master PMI-ACP Exam and Concepts : PMI-ACP Tricks/Tips/Cheat sheet
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is C.
Agile team collectively owns all the project features. As it is the severe issue, therefore, before making change, it would be better to analyze all available information and add it in the product backlog list at the appropriate place so that the team can pick up in the iteration backlog accordingly.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : PMP Tricks/Tips/Cheatsheet
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
Teams work best when they have safe environment to experiment and are allowed to make mistakes. Scrum Master should try to enforce such environment.
Tips/Tricks/Cheat sheet to master PMI-ACP Exam and Concepts : PMI-ACP Tricks/Tips/Cheat sheet
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is A.
Teams work best when they have safe environment to experiment and are allowed to make mistakes. Scrum Master should try to enforce such environment.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : PMP Tricks/Tips/Cheatsheet
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is B.
In Scrum, it is the responsibility of the Product Owner to collaborates with stakeholders and arrange items in the product backlog in the descending order on the basis of the business value.
Tips/Tricks/Cheat sheet to master PMI-ACP Exam and Concepts : PMI-ACP Tricks/Tips/Cheat sheet
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is B.
In Scrum, it is the responsibility of the Product Owner to collaborates with stakeholders and arrange items in the product backlog in the descending order on the basis of the business value.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : PMP Tricks/Tips/Cheatsheet
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
No. of iterations required to complete the project = 500/25 = 20
No. of weeks required to complete the project = 20*3 = 60 weeksTips/Tricks/Cheat sheet to master PMI-ACP Exam and Concepts : PMI-ACP Tricks/Tips/Cheat sheet
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is C.
No. of iterations required to complete the project = 500/25 = 20
No. of weeks required to complete the project = 20*3 = 60 weeksTips/Tricks/Cheatsheet to master PMP Exam and Concepts : PMP Tricks/Tips/Cheatsheet
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
It is the responsibility of the Product Owner to clearly explain user stories to the team.
Tips/Tricks/Cheat sheet to master PMI-ACP Exam and Concepts : PMI-ACP Tricks/Tips/Cheat sheet
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is C.
It is the responsibility of the Product Owner to clearly explain user stories to the team.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : PMP Tricks/Tips/Cheatsheet
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
The team is following Kanban in this question. After visualizing the workflow and putting it on the whiteboard, team introduces Work in Progress (WIP) limits.
Tips/Tricks/Cheat sheet to master PMI-ACP Exam and Concepts : PMI-ACP Tricks/Tips/Cheat sheet
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is D.
The team is following Kanban in this question. After visualizing the workflow and putting it on the whiteboard, team introduces Work in Progress (WIP) limits.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : PMP Tricks/Tips/Cheatsheet
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
This situation describes the need to “compare”. The only choice that compares project results is a variance analysis.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : PMP Tricks/Tips/Cheatsheet
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
Earlier process efficiency = Value added time / Total Time = 18 / (18 + 18) = 50 %
Now process efficiency = Value added time / Total Time = 18 / (18 + 9) = 67 %
Tips/Tricks/Cheat sheet to master PMI-ACP Exam and Concepts : PMI-ACP Tricks/Tips/Cheat sheet
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
admin
KeymasterCorrect answer is C.
Earlier process efficiency = Value added time / Total Time = 18 / (18 + 18) = 50 %
Now process efficiency = Value added time / Total Time = 18 / (18 + 9) = 67 %
Tips/Tricks/Cheat sheet to master PMP Exam and Concepts : PMP Tricks/Tips/Cheat sheet
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge -
AuthorPosts