KeymasterCorrect answer is D.
Individual teams decide the size of story points based upon their own estimations, which cannot be compared across teams. Since velocity is the number of story points completed during an iteration, therefore, velocity too cannot be compared between two different teams.
PMP/Agile Useful Resources : PMP/Agile ResourcesPass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
Individual teams decide the size of story points based upon their own estimations, which cannot be compared across teams. Since velocity is the number of story points completed during an iteration, therefore, velocity too cannot be compared between two different teams.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
Continuous integration involves frequent integration of new piece of work into existing product and ensuring nothing breaks down during integration.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
Continuous integration involves frequent integration of new piece of work into existing product and ensuring nothing breaks down during integration.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions ChallengeStudy Groups: Facebook Whatsapp Telegram
-
This reply was modified 3 weeks, 2 days ago by
admin.
admin
KeymasterCorrect answer is B.
Since zero story points are completed so the burdown graph would become flat. Thus slope would become zero.
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is B.
Since zero story points are completed so the burdown graph would become flat. Thus slope would become zero.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is B.
Big user stories are normally known as Epics.
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is B.
Big user stories are normally known as Epics.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
Team should re-evaluate its velocity. Addition of new members may either increase the velocity due to increased capacity or decrease velocity as training may be required which would cause team members to switch from project work.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
Team should re-evaluate its velocity. Addition of new members may either increase the velocity due to increased capacity or decrease velocity as training may be required which would cause team members to switch from project work.
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
Agile coach is responsible for guiding teams through the Agile implementation. He/She helps in training teams on the agile methodology. They are responsible for encouraging all team members and leadership to embrace the agile method.
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
Agile coach is responsible for guiding teams through the Agile implementation. He/She helps in training teams on the agile methodology. They are responsible for encouraging all team members and leadership to embrace the agile method.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
Dot Voting is an Agile technique to prioritize issues, requirements, etc. Triple Nickel is used to generate ideas in the retrospective. Planning Poker is used for estimation and Fishbone analysis is used for root cause analysis.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
Dot Voting is an Agile technique to prioritize issues, requirements, etc. Triple Nickel is used to generate ideas in the retrospective. Planning Poker is used for estimation and Fishbone analysis is used for root cause analysis.
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is A.
Gold plating means adding more features to please the customer which was not agreed upon in the scope or product backlog.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challenge -
This reply was modified 3 weeks, 2 days ago by
-
AuthorPosts