KeymasterCorrect answer is B.
Scrum Team should be fully dedicated to the project on which they are working upon. Since Project switching is kind of waste and if Sameera is getting work for previous project too so chances are there that the current project may suffer, if not now then may be in the future. Daniel, being the scrum master, should protect his team from the distractions and discuss the situation with Sameera’s manager that let her fully dedicated to the Project ABC only.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
Earlier process efficiency = Value added time / Total Time = 18 / (18 + 36) = 33 %
Now process efficiency = Value added time / Total Time = 18 / (18 + 20) = 47 %
Imrpovement in Process Efficiency = 47% – 33% = 14%
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
Earlier process efficiency = Value added time / Total Time = 18 / (18 + 36) = 33 %
Now process efficiency = Value added time / Total Time = 18 / (18 + 20) = 47 %
Imrpovement in Process Efficiency = 47% – 33% = 14%
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
Helped, Hindered, Hypothesis is being used in the closing stage of retrospective in which we list down what helped during the retrospective, what were the hindrances and what hypothesis we would adopt in future retrospectives to make it more effective.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
Helped, Hindered, Hypothesis is being used in the closing stage of retrospective in which we list down what helped during the retrospective, what were the hindrances and what hypothesis we would adopt in future retrospectives to make it more effective.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
According to Speed B. Leas, this situation is Level 4 conflict. In this level, conflict becomes more ideological and polarized and people feel that the other group is always wrong.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is C.
According to Speed B. Leas, this situation is Level 4 conflict. In this level, conflict becomes more ideological and polarized and people feel that the other group is always wrong.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
In Scrum, only fully completed user stories contributes towards velocity. Since User Stories 1, 2, and 3 are completed, therefore, they will contribute towards velocity.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
In Scrum, only fully completed user stories contributes towards velocity. Since User Stories 1, 2, and 3 are completed, therefore, they will contribute towards velocity.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
Spikes are of short duration cycles which development team use to learn new approach and gain knowledge about something.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
Spikes are of short duration cycles which development team use to learn new approach and gain knowledge about something.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
Generalizing Specialists can help to resolve hand-offs issue, where information gets lost with each hand-off. Since members can perform multiple tasks, therefore, they can share the load and avoid peaks and troughs. Also, it would help to remove bottlenecks.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is D.
Generalizing Specialists can help to resolve hand-offs issue, where information gets lost with each hand-off. Since members can perform multiple tasks, therefore, they can share the load and avoid peaks and troughs. Also, it would help to remove bottlenecks.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is B.
WIP limits along with Kanban board helps in reducing the risk of tied-up capital, rework, and optimize throughput of the work.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challengeadmin
KeymasterCorrect answer is B.
WIP limits along with Kanban board helps in reducing the risk of tied-up capital, rework, and optimize throughput of the work.
Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge -
AuthorPosts