PMP Question 38

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #5087
    admin
    Keymaster

    A project has seven activities A,B,C,D,E,F and G. Activity A B and D can start anytime. Activity A takes 3week to complete. Activity B takes 5week , activity D takes 11 week to complete. Activities A and B must be completed before activity C can start. Activity C requires 6 week to complete. Activities B.C and D must be completed before Activity E can start. Activity E requires 2 week to complete. Activity F takes 4 week and can start as soon as Activity C completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activity F and G must be completed for the project to be completed. What is the critical path?

    A Start—A-C-F-End
    B Start—B-C-E-G-End
    C Start—D-E-G-End
    D Start—B-C-E-G-End and Start—D-E-G-End

    #5088
    admin
    Keymaster

    The correct answer is D.

    Both critical paths have durations of 16 weeks. Since 16 is the longest duration of paths, you have two critical paths.

    Pass PMP in the First Attempt : PMP Strategy

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    #7818
    Lakshita
    Participant

    What will be the network diagram for this ?

    #8783
    admin
    Keymaster

    Network Diagram