PMP Question 292

Home Forums PMP Questions and Answers Discussion PMP Question 292

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #10710
    admin
    Keymaster

    Peter is performing an audit of the projects executed by Organization ABC. He found that in one of the projects, Mary (project manager) does not consider the network diagram as part of Identify risk process. What information she might had missed?

    a) Few activities
    b) Activity Network details
    c) Few Stakeholders
    d) Activities converging at or diverging from any activity

    #10711
    admin
    Keymaster

    Correct answer is D.

    In the network diagram when many activities converge to single activity or diverge from single activity then risk increases if that activity is not properly managed and completed.

    Video Tutorials : PM Video Tutorials

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.