PMP Question 28

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #4827
    admin
    Keymaster

    A project manager has a complex problem to solve and made a decision about what needed to be done. A few months later, the problem resurfaced, what did the project manager MOST likely not do?

    a) Proper risk analysis
    b) Confirm that the decision solved the problem
    c) Have the project sponsor validate the decision
    d) Use an Ishikawa diagram

    #4828
    admin
    Keymaster

    The correct answer is B.

    “Who has time,” you might say, “to determine if each problem is really solved?” One could respond with, “Who has time not to do this? Who has time to deal with the same problem twice?” The final steps of problem solving include: implement a decision, review it, and confirm that the decision solved the problem.

    Pass PMP in the First Attempt : PMP Strategy

    Revise PMP ConceptsPMP Concepts