    Team is working on the project ABC. It encountered problem in an activity with the free float. Due to this, project manager extended its duration. What is MOST likely to be affected in this situation?

    a. Resource schedules
    b. Project duration
    c. Start date of the successor activity
    d. Scope management plan

    #10414
    admin
    Keymaster

    Correct answer is A.

    Since an activity with float will not affect the project duration as long as any delay is not greater than the float, choice B could not be best. Choice D cannot be best as this situation is not related to scope, just time. An activity with free float means it has time where it can be delayed without impacting the next activity. Therefore, choice C cannot be best. Any delay in when an activity is to be completed will most likely impact resources schedules.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.