PMP Question 237

Home Forums PMP Questions and Answers Discussion PMP Question 237

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #10394
    admin
    Keymaster

    In the project ABC, customer requested some changes directly to the development team. Development team made the change without informing Project Manager. When the integration testing was being performed then results were different than what was expected. Which of the following best accounts for this problem?

    a) Improper scope control
    b) Poor communications management plan
    c) Poor quality management plan
    d) Inadequate training

    #10396
    admin
    Keymaster

    Correct answer is A.

    Any scope changes should be noted down and evaluated to know the impact on different areas. If the scope changes are well known then this type of situation will not occur.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.