PMP Question 231

Home Forums PMP Questions and Answers Discussion PMP Question 231

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #10367
    admin
    Keymaster

    Project ABC is not going well. Both the cost variance and the schedule variance are negative, but the cost variance is lower than the schedule variance. What would be the BEST explanation for this situation?

    a) The project under spent because all work was not completed, but overspent for work that was done.
    b) The project overspent due to increased costs yet completed some activities faster.
    c) The project activities took longer than expected, but costs were lower.
    d) The project under spent, because costs were lower than planned and activities were easier to complete than planned.

    #10368
    admin
    Keymaster

    Correct answer is A.

    Both cost and schedule variances are negative and only option A mentions about it.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.