PMP Question 214

Home Forums PMP Questions and Answers Discussion PMP Question 214

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #10278
    admin
    Keymaster

    During the middle of the project, Project Manager realizes that some part of the work is not captured in WBS. In order to accommodate it, Project Manager had to raise change request. What would be the best option to do as a result of this situation?

    a. Revisit the WBS
    b. Add reserve in the project budget
    c. Extend the timeline of the project
    d. Inform CCB that such change request may come again

    #10279
    admin
    Keymaster

    Correct answer is A.

    In such situation, it is better to revisit the WBS and check if more scope is missing or not.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.