    Sara is working as the Project Manager. She worked with the team to identify all risks and the response in the event of risk occurrence. However, for one of the risk, even after trying all possible options she could not identify suitable response. Which risk response strategy would be better to apply here?

    a. Avoidance
    b. Mitigation
    c. Acceptance
    d. Transference

    #9437
    admin
    Keymaster

    Correct answer is C.

    It is not possible to develop response strategy for all risks. In such scenarios, it is better to accept the risk.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material Jobs

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.