Correct answer is D.
Expected Monitory Value (EMV) = Probability × Impact
Calculate both positive and negative values and then add them.
Project A EMV : 0.6 × $100,000 – 0.4 × $100,000 = $60,000 – $40,000 = $20,000 profit
Project B EMV : 0.5 × $200,000 – 0.5 × $200,000 = $100,000 – $100,000 = $0 profit
Project C EMV : 0.4 × $150,000 – 0.6 × $100,000 = $60,000 – $60,000 = $0 profit
Project D EMV : 0.7 × $100,000 – 0.3 × $150,000 = $70,000 – $45,000 = $25,000 profit
Since EMV of Project D is the highest, therefore, the company should do Project D.
PMP/Agile Useful Resources : PMP/Agile Resources
World of Project Management : Mobile App
Jobs : PM Jobs
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram