PMP Question 205

Home Forums PMP Questions and Answers Discussion PMP Question 205

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #9424
    admin
    Keymaster

    Project A has a 60% chance of $100,000 profit and a 40% chance of $100,000 loss. Project B has a 50% chance of $200,000 profit and a 50% chance of $200,000 loss. Project C has a 40% chance of $150,000 profit and a 60% chance of $100,000 loss. Project D has a 70% chance of $100,000 profit and a 30% chance of $150,000 loss. If the company can execute only 1 project then based upon EMV, which project should be selected ?

    a. Project A
    b. Project B
    c. Project C
    d. Project D

    #9426
    admin
    Keymaster

    Correct answer is D.

    Expected Monitory Value (EMV) = Probability × Impact
    Calculate both positive and negative values and then add them.
    Project A EMV : 0.6 × $100,000 – 0.4 × $100,000 = $60,000 – $40,000 = $20,000 profit
    Project B EMV : 0.5 × $200,000 – 0.5 × $200,000 = $100,000 – $100,000 = $0 profit
    Project C EMV : 0.4 × $150,000 – 0.6 × $100,000 = $60,000 – $60,000 = $0 profit
    Project D EMV : 0.7 × $100,000 – 0.3 × $150,000 = $70,000 – $45,000 = $25,000 profit

    Since EMV of Project D is the highest, therefore, the company should do Project D.

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Jobs : PM Jobs

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & Answers: Question & Answers

    Revise PMP Concepts: PMP Concepts

    PMP Tips & Tricks: PMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.