    There is an upcoming meeting for the project and the concerned stakeholders want to see the comparison of the actual project results and planned results. What does the Project Manager should use?

    a. Trend report
    b. Forecasting report
    c. Status report
    d. Variance report

    #9317
    admin
    Keymaster

    Correct answer is D.

    This situation describes the need to “compare”. The only choice that compares project results is a variance analysis.

    World of Project Management : Mobile App

    Jobs : PM Jobs

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & Answers: Question & Answers

    Revise PMP Concepts: PMP Concepts

    PMP Tips & Tricks: PMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.