PMP Question 199

Home Forums PMP Questions and Answers Discussion PMP Question 199

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #9289
    admin
    Keymaster

    An agile team wanted to improve its process. They used value stream map to check value adding and non-value adding activities. Earlier Value added time was 18 minutes and non-value added time was 18 minutes. After analysing scope of improvement, value added time was 18 minutes and non-value added time was 9 minutes. By what percentage process efficiency got increased?

    a. 50%
    b. 67%
    c. 17%
    d. 57%

    #9290
    admin
    Keymaster

    Correct answer is C.

    Earlier process efficiency = Value added time / Total Time = 18 / (18 + 18) = 50 %

    Now process efficiency = Value added time / Total Time = 18 / (18 + 9) = 67 %

    Imrpovement in Process Efficiency = 67% – 50% = 17%

    World of Project Management : Mobile App

    Jobs : PM Jobs

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & Answers: Question & Answers

    Revise PMP Concepts: PMP Concepts

    PMP Tips & Tricks: PMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.