    Sara is the Scrum Master of the team. For the past 2 sprints, she analysed that the development team is not able to complete the user stories they committed for the respective sprints. While finding out the root cause during retrospective meeting, Sara found that the development team gets frequent request to provide support for the already released software which hinders their ongoing work. What should she do next ?

    a. Discuss with Product Owner and the development team and add maintenance tasks in the product and sprint backlogs
    b. Ask team to commit to lesser amount of work to handle such requests
    c. Create a separate team to handle after release support requests
    d. Ask team to refuse such requests

    #9273
    admin
    Keymaster

    Correct answer is A.

    All such requests should be estimated, prioritized and added to the product backlog so that it can be included in the sprint backlog based upon priority.

    World of Project Management : Mobile App

    Jobs : PM Jobs

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & Answers: Question & Answers

    Revise PMP Concepts: PMP Concepts

    PMP Tips & Tricks: PMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.