PMP Question 193

Home Forums PMP Questions and Answers Discussion PMP Question 193

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #9164
    admin
    Keymaster

    An Agile team is managing its work in progress on a Kanban board. After few weeks, WIP limits reached and the team cannot take more work to do from the “Ready” state. What should the team do first?

    a. Discuss what to be done to move work from WIP state to Done state
    b. Discuss how can we increase the WIP limit
    c. Discuss who is not working properly in the team
    d. Discuss to incorporate method other than Kanban to track progress

    #9166
    admin
    Keymaster

    Correct answer is A.

    When the WIP limits are reached, the team cannot pull work from the left column. The team should discuss how as a team they can move work from WIP column to the done column.

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material Jobs

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.