    After checking variances in the schedule, Project Manager raised the change request in respective areas to the change control board and got it approved. What is the NEXT thing to do?

    a. Check the impact on cost and scope
    b. Notify stakeholders affected by the change
    c. Check again with change control board if any other approval is required
    d. Change the WBS

    #9155
    admin
    Keymaster

    Correct answer is B.

    Once the change is approved or rejected, it is better to inform the stakeholders affected by it.

    World of Project Management : Mobile App

    PMP 2021 Extra Study Material by PMI : PMP 2021 Extra Study Material Jobs

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.