PMP Question 187

Home Forums PMP Questions and Answers Discussion PMP Question 187

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #9140
    admin
    Keymaster

    Steve had been assigned as the developer for the Work Package ABC. When David, Project Manager, was reviewing the overall work, he found that Steve is doing it differently as mentioned in the WBS dictionary. What should Steve do first in this situation?

    a. Check if the alternative way will change the scope of the the work package ABC
    b. Check with the team if Steve is doing right or not
    c. Check if the alternative way is requested by the functional manager
    d. Ask Steve to stop work and replace him with other developer

    #9141
    admin
    Keymaster

    Correct answer is A.

    First thing to check is if the overall scope of the work package is same or not . Team members have got some flexibility to do work if they are not changing the scope of the work package.

    World of Project Management : Mobile App

    Jobs : PM Jobs

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.