PMP Question 186

Home Forums PMP Questions and Answers Discussion PMP Question 186

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #9131
    admin
    Keymaster

    Robin has been assigned Project Manager of the project ABC. He is in the process of determining what all resources would be required in the project. When should Robin start this process?

    a. After developing the project schedule and creating the scope baseline
    b. Before generating the project scope statement and activity network diagram
    c. Before developing the project schedule but after creating the activity network diagram
    d. After developing the project schedule and project scope statement

    #9134
    admin
    Keymaster

    Correct answer is C.

    Estimate Activity Resources process comes after Sequence Activities but before Develop Schedule.

    World of Project Management : Mobile App

    Jobs : PM Jobs

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.