Correct answer is D.
EV = CPI x AC = 1.1 x $800M = $880M
CV = $880M – $800M = $80M
SV = $880M – $890M = -$10M
SPI = $880M / $890M = 0.99
Since CV is positive, therefore, project is under budget.
Since SV is negative, therefore, project is behind schedule.