    After jotting down all the deliverable, project team sub-divides work packages into more smaller and manageable components. What the team is doing here?

    a. Decomposition
    b. WBS creation
    c. Network diagram creation
    d. Identifying owners for each components

    #9124
    admin
    Keymaster

    Correct answer is A.

    Since the team is dividing work packages, therefore, the team is basically creating activity list out of work package. This is known as Decomposition.

    World of Project Management : Mobile App

    Jobs : PM Jobs

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.