PMP Question 181

Home Forums PMP Questions and Answers Discussion PMP Question 181

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #9102
    admin
    Keymaster

    Project Manager of the buyer organization shares with the Senior Management that a part of the project needs to be developed from the third party. Senior Management told the project manager to go for fixed price contract. An advantage of the fixed price contract for the buyer is?

    a. Cost risk is lower
    b. Cost risk is higher
    c. Cost risk is not taken into consideration
    d. Risk is shared by both the parties

    #9103
    admin
    Keymaster

    Correct answer is A.

    If you look from buyer’s perspective, cost risk is lower in fixed price contract. In fixed price contract, seller has the most cost risk.

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.