Correct answer is B.
This network diagram has two paths:
Path 1 : Start, 1, 2, 3, End
Path 2 : Start, 1, 4, End
Before change:
Path 1 length : 10 weeks
Path 2 length : 9 weeks
Therefore, critical path is Path 1.
After change:
Path 1 : 10 weeks
Path 2 : 11 weeks
Therefore, now critical path is Path 2 whose duration is 11 weeks.
World of Project Management : Mobile App
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area based Quiz:
20 Questions Challenge
50 Questions Challenge
PMP Agile based Quiz:
20 Questions Challenge
50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram