    Team is following Sprint to execute the ongoing project. Team meets during the Sprint planning and decided what they will be executing during the Sprint. One of team member asked Sara, Scrum Master, about the reasons in which Sprint can be cancelled. In which of the following options, sprint can be cancelled?

    a. When the Scrum Master says sprint can be cancelled.
    b. When there is major change in the development team.
    c. When the Sprint Goal becomes obsolete
    d. Sprint cannot be cancelled in any situation

    #9074
    admin
    Keymaster

    Correct answer is C.

    When the Sprint goal for which the sprint was undertaken becomes obsolete then the Sprint can be cancelled.

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.