Correct answer is B.
It is always better to involve the team for the discussion as it taps wider knowledge base and helps in enhancing the idea and removing any bottlenecks. Solutions to the problems should not be discussed in the Daily scrum meeting. Once the team comes up with the viable solution then may be it can be discussed with Product Owner and prioritized in the backlog.