    During the middle of the project, Project Manager realises that some part of the work is not captured in WBS. In order to accomodate it, Project Manager had to raise change request. What would be the best option to do as a result of this situation?

    a. Revisit the WBS
    b. Add reserve in the project budget
    c. Extend the timeline of the project
    d. Inform CCB that such change request may come again

    #8996
    admin
    Keymaster

    Correct answer is A.

    In such situation, it is better to revisit the WBS and check if more scope is missing or not.

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.