    Company ABC has started new project. Project Manager is selected but the team is yet to be finalized. Based upon past experiences, it seems the company can complete the project within time. However, during the team selection, Project Manager started experiencing difficulties in finding out the members. What should Project Manager focus more on in this situation?

    a) Risk Identification
    b) Project organization chart
    c) Creation of RAM
    d) Resource Limited Schedule

    #8980
    admin
    Keymaster

    Correct answer is D.

    In this situation, schedule developed based upon resource limitation is most helpful to the Project Manager. This will help him to plan activities and show the true picture of schedule to all stakeholders.

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.