Company ABC has started new project. Project Manager is selected but the team is yet to be finalized. Based upon past experiences, it seems the company can complete the project within time. However, during the team selection, Project Manager started experiencing difficulties in finding out the members. What should Project Manager focus more on in this situation?
a) Risk Identification
b) Project organization chart
c) Creation of RAM
d) Resource Limited Schedule