PMP Question 163

Home Forums PMP Questions and Answers Discussion PMP Question 163

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #8966
    admin
    Keymaster

    In the retrospective meeting, team discussed few measures to reduce the build time from 10 minutes to 5 minutes. They found that a particular module takes more time and decided to refactor it to improve build time. Team had done such improvements in the past. When the team shared this with Product Owner, product owner asked to implement it in future iterations. What is the problem with this goal?

    a. It is not specific
    b. It is not measurable
    c. It is not attainable
    d. It is not timely

    #8967
    admin
    Keymaster

    Correct answer is D.

    There is no specified time within which the target is to be achieved.

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.