    Vinay, Project Manager, just reviewd and completed the WBS and the WBS dictionary with the help of his team. Vicky, Project Sponsor, asked Vinay to publish risk register and responsibility assignment matrix so that everyone on the team would know about their roles. What Vinay should do next?

    a. Create activity list
    b. Identify roles and responsibilities of team members
    c. Identify risks
    d. Create project management plan

    #8941
    admin
    Keymaster

    Correct answer is A.

    After completion of WBS and WBS dictionary, activity list is generated.

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.