PMP Question 157

Home Forums PMP Questions and Answers Discussion PMP Question 157

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #8778
    admin
    Keymaster

    During the iteration planning, team commits to complete 5 stories worth 20 story points. However, during the iteration, it seems team would be able to complete 4 stories worth 18 story points only. As a scrum master, what should you suggest the team.

    a. Since the team committed for 20 story points so the team should work overtime to meet their target.
    b. Do less testing and try to complete all 5 stories
    c. Complete 4 stories only worth 18 story points
    d. Ask Product Owner if iteration length can be increased

    #8780
    admin
    Keymaster

    Correct answer is C.

    Team should complete (development and testing) 4 stories worth 18 story points. In the iteration retrospective, team can discuss the reasons of not meeting the target and then can plan accordingly for future iterations.

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.