    In the project ABC, Simon (customer) asked for aluminium bars whereas the team think that steel bars would better serve the overall project. Kiara, Product Owner, discussed with Simon but Simon ask for aluminium bars only. What should Kiara do in this situation?

    a. Raise the issue to her senior management
    b. Discuss again with Simon at later point of time
    c. Use aluminium bars instead of steel bars
    d. Use steel bars instead of aluminium bars

    #8472
    admin
    Keymaster

    Correct answer is C.

    Product Owner should discuss pros and cons with customer but finally follow customer’s request. Since Kiara discussed with Simon and Simon gave confirmation for aluminium bars so she should use aluminium bars only.

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.