    Project ABC is not going well. Both the cost variance and the schedule variance are negative, but the cost variance is lower than the schedule variance. What would be the BEST explanation for this situation?

    a) The project under spent because all work was not completed, but overspent for work that was done.
    b) The project overspent due to increased costs yet completed some activities faster.
    c) The project activities took longer than expected, but costs were lower.
    d) The project underspent, because costs were lower than planned and activities were easier to complete than planned.

    #7937
    admin
    Keymaster

    Correct answer is A.

    Both cost and schedule variances are negative and only option A mentions about it.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.