    In the project ABC, customer requested some changes directly to the development team. Development team made the change without informing Project Manager. When the integration testing was being performed then results were different than what was expected. Which of the following accounts for this problem?

    a) Improper scope control
    b) Poor communications management plan
    c) Poor quality management plan
    d) Inadequate training

    #7679
    admin
    Keymaster

    Correct answer is A.

    Any scope changes should be noted down and evaluated to know the impact on different areas. If the scope changes are well known then this type of situation will not occur.

    Pass PMP in the First Attempt : PMP Strategy

    PMI 200 PMP questions Solution : PMI-PMP Practice Exam

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.