    In the Project ABC, project manager felt that due to lack of participation of stakeholders, project is not progressing smoothly. Project manager wants stakeholders to be more engaged in the project. How can it be best achieved?

    a. Involve stakeholders to review the requirements on regular basis
    b. Share status reports with stakeholders
    c. Invite stakeholders in the team status meetings
    d. Invite stakeholders in the project milestone parties

    #7626
    admin
    Keymaster

    Correct answer is A.

    Involving stakeholders in the requirements review will help in several ways as it not only helps to clear doubts regarding requirements but also generate interest of stakeholders in following up the development status of the requirements.

    Pass PMP in the First Attempt : PMP Strategy

    PMI 200 PMP questions Solution : PMI-PMP Practice Exam

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.