Team has been working on difficult issues 9n a critical project. During the discussion, few members disagreed on how the work has to be done. Project sponsor had to intervene to resolve the issue. During later phase, project manager discovered that a particular task was not completed as it was intended to be done. What did the project manager NOT do?
a) Ask team members responsible for the work to describe how the task would be done
b) Ensure functional managers should be involved during development
c) Provide training to team members
d) Organize team building sessions